A picture is worth a thousand words…

We have so many updates on the Welcome Center and surrounding areas that we decided to do it with pictures. See below each shot for information. The logging is complete and the stumps are currently being removed. Hard to take good pictures of what is no longer there, but it certainly looks much better once it is complete and all smoothed back out. The grass is starting to sprout and the upcoming rains next week will certainly help it to grow.

The roof is on! The front porch is set with the galvanized beams and the concrete slab for the porch will be poured in the next 8 days.
Along with the porch of the Welcome Center, the porch for the Camp Office is also almost ready to be poured. It is going to be a great addition to our camp facilities to have an official place to check in, come for assistance etc.
The next big pour for the basement floor is also ready. That will happen on the 2nd and 3rd of December. After that, the stairs to the upper two floors can be put into place.
The Welcome Center of many angles. Just a shot to show you how complex the framing for the house was. It is a huge relief to get it all completed. The windows are on site and will be installed in the next week. ALL 36 of them!
In the right side of this photo, you can see yellow caution tape around part of the septic tank pits. Two tanks are being delivered on Monday and that work will be complete before the rains set in.

We will share pictures soon of the next concrete pours and window install. Lots to do inside, but with a roof on, all things are possible now.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s